References

Year No. Boiler type Country Boiler output HD bar/ °C Scope of service Duration
2010 1 waste boiler Austria 35,4 t/h 40/400 wall replacement top 2nd pass,
bend installation , part. replacement ÜII, replacement of
protective shells, cladding ca. 48 m² combustion
chamber bottom, revision
2 weeks
2010 1 biomass Germany 31 t/h 52/420 grate revision,
replacement superheater II a. III
2 weeks
2010 1 biomass Germany 78,8 t/h 64/450 replacement ÜIII 1 week
2010 1 waste boiler OL1 Switzerland 52 t/h 40/400 conversion ash removal 2nd/3rd pass, pipe replacement
ÜII 5 rows, hand cladding approx. 4 m²
revision
2 weeks
2010 1 waste boiler OL1 Germany 37,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
extensive cladding maintenance, replacement
collector 8 at ÜIII, rapper system revision.
1,5 weeks
2010 1 waste boiler OL3 Switzerland 34 t/h 21/280 annual revision
wall thickness measurements, rapper system revision
2 weeks
2010 1 biomass OL3 23,5 t/h 24/380 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
rapper system revision
1,5 weeks
2010 2 waste boiler VL 2 Germany 42,2 t/h 40/400 rapper system and eco cleansing revision
replacement combustion chamber front wall, extensive
cladding maintenance, hand cladding approx. 15 m²
2,5 weeks
2010 2 waste boiler MK1+ 2 Germany 24,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding, wall replacement in the 2nd pass, rapper
system revision, conversion LUVO vapour supply.
2*4 weeks
2010 1 waste boiler OL3 34 t/h 21/280 annual revision
wall thickness measurements, rapper system revision
2 weeks
2010 2 waste boiler VL1 Germany 42,2 t/h 40/400 rapper system and eco cleansing revision
replacement combustion chamber front wall, extensive
cladding maintenance, hand cladding approx.15 m²
2,5 weeks
2010 1 biomass Germany 51 t/h 61/452 replacement ÜIII
General revision.
1 week
2010 1 waste boiler Germany 73,5 t/h 60/400 annual revision , project management as main contractor,
boiler cleansing, wall thickness measurements,
visual inspections, replacement of top 2nd pass,
replacement of grid pipes, cladding
2nd pass90 m², revision.
2,5 weeks
2009 1 waste boiler OL2 Switzerland 42,8 t/h 40/420 replacement of end superheater and part.
ÜI/2 revision
2 weeks
2009 1 waste boiler OL1 Switzerland 52 t/h 40/400 replacement of 200 m² membrane wall
revision
3 weeks
2009 1 waste boiler OL1 Germany 37,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
Re cladding 2nd pass, replacement of membrane
walls, rapper system revision.
1,5 weeks
2009 1 waste boiler OL3 Switzerland 34 t/h 21/280 annual revision
wall thickness measurements, rapper system revision
2 weeks
2009 1 biomass OL3 Germany 23,5 t/h 24/380 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
rapper system replacement, vaporiser and eco rapper system revision.
1,5 weeks
2009 2 waste boiler VL 2 Germany 42,2 t/h 40/400 rapper system and eco cleansing revision
Superheater renovation.
2,5 weeks
2009 2 waste boiler MK1+ 2 Germany 24,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding, wall replacement, replacement
of Eco pipes, rapper system revision.
2*4 weeks
2009 1 Mwaste boiler OL3 Switzerland 34 t/h 21/280 annual revision
wall thickness measurements, rapper system revision
2 weeks
2009 2 waste boiler VL1 Germany 42,2 t/h 40/400 rapper system and eco cleansing revision
replacement of pre-vaporiser.
2,5 weeks
2009 1 waste boiler Germany 58 t/h 41/410 replacement of approx. 260 m² membrane walls,
Installation of ventilation plant for JuSys Air,
revision
3,5 weeks
2009 1 waste boiler Germany 73,5 t/h 60/400 replacement of membrane walls,
cladding rear wall 2nd run.
Revision
2 weeks
2008 2 waste boiler MK1+ 2 Germany 24,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding, rapper system revision, end discs
retrofitting of fittings .
2*4 weeks
2007 2 waste boiler MK1+ 2 Germany 24,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding, rapper system revision.
2*4 weeks
2006 waste boiler Germany 60 t/h 40/400 overall planning
replacement of 52m² membrane walls in the
combustion chamber, cladding 89m² , fire-proof 570 m²
3 weeks
2006 1 biomass Germany 31 t/h 52/420 grate revision,
replacement superheater II u. III
2 weeks
2006 1 waste boiler OL1 Switzerland 32 t/h 41/400 annual revision
wall thickness measurements, ceram. lining
rapper system revision
2 weeks
2006 2 waste boiler MK1+ 2 Germany 24,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding, replacement of superheater pipes,
rapper system revision.
2*4 weeks
2006 1 biomass Germany 51 t/h 61/452 grate revision,
boiler-side visual inspections.
1 week
2006 1 biomass Germany 78,8 t/h 64/450 replacement of 20m² membrane walls 1 week
2006 1 waste boiler OL1 15 t/h 40/400 annual revision
wall thickness measurements, cladding side walls
2 weeks
2006 2 waste boiler VL1+ 2 Germany 42,2 t/h 40/400 rapper system and eco cleansing revision replacement superheater pipes. 2,5 weeks
2006 1 waste boiler MK3 Germany 32,4 t/h 39/400 replacement of 80m² membrane walls
in the combustion chamber, Cladding, replacement
von superheater pipes, rapper system revision.
2 weeks
2006 1 waste boiler MK4 Germany 32,4 t/h 39/400 replacement of 88m² membrane walls
in the combustion chamber, replacement of superheater
pipes, rapper system revision.
2 weeks
2006 1 waste boiler OL1 Germany 37,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
Cladding 3rd pass, replacement of superheater pipes,
rapper system revision.
1,5 weeks
2006 1 waste boiler OL1 Switzerland 52 t/h 40/400 replacement superheater II 2 weeks
2006 1 waste boiler 35,4 t/h 40/400 replacement superheater III 1,5 weeks
2006 1 hazardous waste boiler 35,4 t/h 40/400 conversion emergency supply water tank 2,5 weeks
2006 1 waste boiler OL3 34 t/h 21/280 annual revision
wall thickness measurements, rapper system revision
2 weeks
2006 1 biomass OL3 23,5 t/h 24/380 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
rapper system revision.
1,5 weeks
2005 1 industrial boiler 160 t/h 106/525 retaining power plant dismantling 3 months
2005 1 biomass 51 t/h 61/452 Graterevision,
boiler-side visual inspections.
1 week
2005 1 biomass 78,8 t/h 64/450 grate revision,
boiler-side visual inspections.
1 week
2005 1 waste boiler OL1 37,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding combustion chamber
1,5 weeks
2005 2 waste boiler MK1+ 2 24,8 t/h 40/400 annual revision , project management as main contractor,
boiler cleansing, ceramics lining,
wall thickness measurements, visual inspections,
cladding, replacement of superheater pipes,
rapper system revision.
2*4 weeks
2005 1 waste boiler OL1 32 t/h 41/400 annual revision
wall thickness measurements, ceram. lining
rapper system revision
2 weeks
2005 1 waste boiler OL2 15 t/h 40/400 annual revision
wall thickness measurements, Cladding side walls
2 weeks
2005 1 waste boiler OL3 34 t/h 21/280 Annual revision
wall thickness measurements, ceram. lining
Cladding combustion chamber, wall replacement 2nd pass,
rapper system revision
2,5 weeks
2005 1 waste boiler MK1 32,4 t/h 39/400 replacement lower side walls,
cladding.
2 weeks